MEP MATERIALS MAJOR, MINOR & BULK SUBMISSION

01.

HVAC AIR TERMINALS & DAMPERS

• Gathering Material Specifications for the specific material of MEPF services.
• Based on MEPF Design calculations and Equipment schedule we prepare RFQ Package & send to Procurement department / to client as per the agreement and contract.
• Procurement department provides selections for MAJOR / MINOR / BULK Materials.
• Design Engineers receives the selections form Procurement department/form the client and start reviews the Selections based on Project Specifications & Approved design.
• The Approved Material Submittals are forwarded to the Client / Site / Project team to start procurement.

HVAC

CHILLED WATER SYSTEM

PLUMBING MATERIALS

FIRE FIGHTING MATERIALS

ELECTRICAL MATERIALS

Let’s Design Your Success

At Specific Design Consultant LLP, we're here to turn your vision into reality. Whether you’re planning a new project or seeking expert advice for your MEPF (Mechanical, Electrical, Plumbing, and Firefighting) needs, our team is ready to assist.

Scroll to Top